THERMIND THermal Energy stoRage Matching INdustrial Demand with phase change materials.
- Coordinator
- Commissariat a L Energie Atomique Et Aux Energies Alternatives, France
- Runs
- 1 January 2027 to 28 February 2031
- Status
- Running
- EU funding
- €7.5m
- Total cost
- €8.3m
- Partners
- 12 organisations in 8 countries
- Type
- Innovation Action
- Grant agreement
- 101325963
What the project is doing
In the project's own words, from its summary on CORDIS.
Decarbonising industrial process heat in the 150-200 °C range (saturated steam) remains a major challenge despite its wide use in the food & beverage, chemical, textile, and paper industries requiring safe, controllable, and compact heat supply. Concentrated Solar Thermal (CST) particularly fits these requirements, but the mismatch between solar supply and heat demand limits its uptake. Current Thermal Energy Storage (TES) options remain insufficient: sensible heat TES, typically pressurised water tanks in this case, is mature but its low storage density leads to large volumes, high footprint and elevated CAPEX.
Latent heat TES with Phase Change Materials (PCM) offers higher storage density, yet, it has not crossed the “valley of death” to reach industrial adoption. THERMIND bridges this gap by advancing PCM-TES to TRL7. Two TRL5 prototypes from the FRIENDSHIP and HYBRIDplus EU projects are consolidated and comparatively validated, alongside the screening of ≥6 PCMs to select the optimal material-technology combination. This leads to a ≥0.5 MWhth PCM-TES demonstrator integrated with SOLATOM’s CST plant at the Heineken brewery in Spain, operating ≥9 months under real conditions and solar variability to validate performance, safety, and dispatchability.
A digital energy management system optimises solar, storage, and auxiliary renewables, while SSbD, LCA, sLCA, and TEA provide safety, sustainability, and investor-grade evidence. By 2040, a scaled 15 MWhth unit is projected to achieve ≈31 €/MWhth LCOHS (45% below current JRC baselines), enabling annual savings of 1,368 tCO2/year and 547,500 m³/year of natural gas per installation. Bringing together 12 partners across 8 countries - research leaders, technology developers, industrial integrator, engineering authority, operator and market actors - THERMIND delivers the 1st industrially validated PCM-TES solution for saturated steam in Europe, paving the way for large-scale replication and Innovation Fund deployment.
Topics
Who is involved
| Organisation | City | Country | Role |
|---|---|---|---|
| Commissariat a L Energie Atomique Et Aux Energies Alternatives | Paris | France | Coordinator |
| Solar Heat Europe | Bruxelles / Brussel | Belgium | Participant |
| Panepistimio Aigaiou | Mytilini | Greece | Participant |
| Build to Zero SL | Sevilla | Spain | Participant |
| Empresarios Agrupados Internacional SA | Madrid | Spain | Participant |
| Fundacion Tekniker | Eibar Guipuzcoa | Spain | Participant |
| Solatom Csp SL | Valencia | Spain | Participant |
| Universidad De Sevilla | Sevilla | Spain | Participant |
| Lappeenrannan-Lahden Teknillinen Yliopisto Lut | Lappeenranta | Finland | Participant |
| Rina Consulting - Centro Sviluppo Materiali SpA | Roma | Italy | Participant |
| Kungliga Tekniska Hoegskolan | Stockholm | Sweden | Participant |
| Phase Change Material Products Ltd | Peterborough Cambs | United Kingdom | Participant |
Source: CORDIS, European Commission. Data of 5 Nov 2026, reused under the Commission's reuse policy. View on CORDIS · Grant DOI